Overhaul of the turbo aggregate of Blocks B1 and B2

PROJECT DESCRIPTION:
In the overhaul period in 2016, the following is being executed on the B1 Block:
- Demounting and inspection of turbo aggregate bearings
- Inspection of steam sealing gap CVP, CSP, CNP1 and CNP2
- Demounting, inspection, replacement as required and mounting of steam valve sections VP, SP and bypass valve NP
- Revision of all oil pumps
- Demounting, inspection, replacement of parts as required and mounting of bearings and steam sections of turbopump turbine
In the overhaul period in 2016, the following is being executed on the B2 Block:
- Demounting of high-pressure, middle-pressure and low-pressure turbine
- Demounting of servomotor and steam sections of high-pressure, middle-pressure valve and low-pressure bypass valve
- Replacement of the CSP internal cabinet with a new one
- Demounting, overhaul and inspection of turbopump turbine
- Mounting of high-pressure, middle-pressure and low-pressure turbine
- Mounting of servomotor and steam sections of high-pressure, middle-pressure valve and low-pressure bypass valve
- Overhaul of components of lubricating, lifting and regulating oil system
PROJECT: Overhaul of the turbo aggregate of Blocks B1 and B2
FACILITY: “TPP Nikola Tesla” B, Ušće, Blocks B1 and B2
INVESTOR: JP EPS, Belgrade, Thermal Power Plant “Nikola Tesla”, Unit TPP NT B
LOCATION: TPP NT B
YEAR OF REALIZATION: 2016