Installation of technological equipment for delayed coking WP1 and WP2 (DCU Plant) in Oil Refinery Pančevo
PROJECT: INSTALLATION OF TECHNOLOGICAL EQUIPMENT, PROJECT OF RNP DELAYED COKING PLANT WP1 AND WP2 (DCU Plant)
FACILITY: NIS Rafinerija Nafte Pančevo (DCU PLANT)
INVESTOR: NIS-RNP Pančevo
LOCATION: Pančevo
YEAR: 2018-2020
PROJECT DESCRIPTION:
In the period May 2018 – August 2020 we installed furnace technological equipment (stationary and rotary) in Oil Refinery Pančevo within the project of delayed coker unit WP1 AND WP2 (DCU Plant).
- Columns, vessels, filters and heat exchangers,
- Floors and fills in columns,
- Pumps, compressors and mixers
- Air coolers and cooling towers,
- Skid compact units,
- Service cranes,
- Special equipment,
- Replacement of existing equipment with new one during repairs in 2019
Works included unloading, internal transport, preparation for installation, levelling, installation and preservation of equipment until commissioning. Certain equipment required preassembly in the construction site.