5. Reconstruction of three tanks in Oil Refinery Pančevo within the project of delayer coker unit WP2 (DCU Plant)

5. Reconstruction of three tanks in Oil Refinery Pančevo within the project of delayer coker unit WP2 (DCU Plant)

PROJECT: RECONSTRUCTION OF TANKS FOR LIGHT HC SLOP FB-10211 RECONSTRUCTION OF TANK 0711/0714 WITH NEW BLANKETING SYSTEM, RNP DESIGN OF DELAYED COKING UNIT WP2 (DCU Plant)

FACILITY: NIS Rafinerija Nafte Pančevo (DCU PLANT)

INVESTOR: NIS-RNP Pančevo

LOCATION: Pančevo

YEAR: 2019-2020

PROJECT DESCRIPTION:

Three tanks have been reconstructed in Oil Refinery Pančevo in the period 2019-2020 within the project of delayed coker unit WP2 (DCU Plant) including:

 

Tank FB-1021 for light HC slop was reconstructed to a great extent, mostly due to damage caused by 1999 NATO bombing, where damage on the shell was the most severe.

 

Reconstruction work included: floor repair and installation of DWS floor, shell repair, replacement of roof structure and roof sheets, restoring old and installation of new connections, modification of fire protection system, installation of new platform, installation of floating decks, rehabilitation of foundations and gutters.

 

Tanks FB-0711/0714 have been reconstructed due to corrosion damage caused by lack of corrosion protection and operating conditions, as well as because new blanketing system was required.

 

Reconstruction work included: floor repair and installation of DWS floor, shell repair, replacement of roof structure and roof sheets, restoring old and installation of new connections, modification of fire protection system, installation of new platform, installation of floating decks and installation of new blanketing system.

 

Work included design, purchase and delivery of materials, equipment and work

Construction of two new storage tanks in Oil Refinery Pančevo in the delayed coker unit WP1 (DCU Plant)
Reconstruction of tank FB-2003