Overhaul of the A1 Block turbine

PROJECT DESCRIPTION:

In the overhaul period in 2016, the following is being executed:

  • Demounting of low-pressure turbine
  • Revision and replacement of low-pressure turbine diaphragms
  • Demounting, inspection, test and mounting of turbo aggregate bearings
  • Inspection of regulating system components
  • Inspection of mechanical generator section components
  • Mounting of low-pressure turbine

PROJECT: Overhaul of the A1 Block turbine

FACILITY: “TPP Kostolac” A, Kostolac

INVESTOR: JP EPS, Belgrade, company “TPP-KO Kostolac“

LOCATION: “TPP Kostolac” A, Kostolac

YEAR OF REALIZATION: 2016.